// Wattay Airport Terminal
Expansion Project
Wattay Airport Terminal
Expansion Project
Project duration: August 2014 to September 2020
Client: Department of Civil Aviation / MPWT
A US$70 million expansion and renovation project of the international and domestic passenger terminals.
![](https://www.laoconsulting.com/DEV/wp-content/uploads/2021/06/wattay3.jpg)
As JV partner, LCG provided the following services with the international partners:
- Carried out engineering surveys including topographical, geotechnical, and material availability surveys;
- Prepared detailed design (architectural, structural, electrical, mechanical, and infrastructure designs);
- Prepared detailed bill of quantities and technical specifications;
- Carried out construction supervision of the works and handover process as well as monitoring of defects during the defect’s liability period; and
- Assisted in the implementation of the Environmental Management and Monitoring Plan (EMMP).
![](https://www.laoconsulting.com/DEV/wp-content/uploads/2021/06/wattay2.jpg)
This included the design and construction of airport maintenance workshop, design and construction of temporary domestic passenger terminal building, design and construction/installation of new utilities, design and construction of new infrastructural works with the following details:
- International passenger terminal (3-storey) expansion 11,500m2, renovation 3,200m2, including related equipment (boarding bridges, baggage handling system, x-ray machines, metal detectors and ramp buses);
- Domestic passenger terminal (2-storey) expansion 6,500 m2 including related equipment (boarding bridges, baggage handling system, x-ray machines, metal detectors and ramp bus); and
- Infrastructure works (pavement: 27,700m2, box culverts, landscaping, taxiway lighting).